Steel Mill Reference

JSW Steel — 180 t BOF Working Lining & 400 t Torpedo Car Lining

JSW Steel — 180 t BOF Working Lining & 400 t Torpedo Car Lining
India

Project Overview

XZK supplies MgO-C working linings with bottom purging assemblies for 180 t BOF converters and ASC linings for 400 t torpedo cars at JSW Steel.

Client & Location India
Furnace Specification 180 t BOF converter + 400 t torpedo car
Performance Result Matched machined purging assembly removed a forcing position — campaign now set by the lining, not the plug

JSW Steel's 180 t BOF and 400 t torpedo car scope is a case where the decisive engineering detail was small: the converter's bottom purging assembly was supplied as a matched, machined set rather than as a plug with separately sourced furniture.

Client and Plant Context

JSW operates high-productivity converters with a hot metal balance that leaves little slack, and 400 t torpedo cars sized accordingly. In that configuration, unscheduled converter downtime propagates quickly: either torpedos queue and cool, or the steelmaking rate falls. The plant's refractory requirement is therefore campaign predictability at least as much as campaign length.

The Problem as Diagnosed

The converter's forcing position was the bottom purging assembly, failing on a shorter cycle than the working lining. Failure analysis pointed at geometry rather than chemistry: penetration around the assembly begins with a gap, and gaps begin with a seat that was worn, a dimension out of tolerance, or an installation that compressed the wrong interface. Once steel finds the path, gas flow becomes erratic, stirring quality falls, and the plug change becomes an emergency instead of a plan — and the plug's metallurgy never gets the chance to matter.

On the torpedo side, the duty was the familiar three-fold one: slag erosion, thermal cycling on every trip, and reagent attack from the desulfurisation practice. A single-mechanism material would have addressed one of the three.

Engineering Approach

  • Bottom purging — plug, well block and seat supplied as one engineered set, every interface inspected against the drawing and critical assemblies dry trial-fitted at the factory before shipment. The plug type was selected by steel route: directional or slit-type for robustness against penetration and easier inspection, which suits a high-productivity shop with infrequent plug changes.
  • Converter working lining — zoned: impact-resistant charge pad grades, oxidation-resistant slag line and metal zone MgO-C with the antioxidant package tuned to slag basicity and FeO, taphole seating and sleeve blocks with matched waterless taphole clay, and a low-carbon safety lining.
  • 400 t torpedo cars — ASC brick zoned for impact pad, barrel, slag line and throat, with dedicated throat and mouth shapes and a matching castable, because the throat is the position that fails first on almost every torpedo fleet.

Supply, Documentation and Logistics

The purging assemblies shipped with flow-test records — flow rate at working pressure, opening pressure, and back-pressure behaviour at low flow — plus the inspection report from the factory dry trial-fit, so the receiving check verified what had been verified at manufacture. Torpedo and converter material carried Certificates of Analysis in the same format, and shapes were palletised by zone.

Installation and Commissioning

Installation supervision for the first matched assembly covered the three known failure points: seat surface clean and undamaged before setting, joint mortar to the specified grade and thickness, and the first heats run to the plug's designed stirring profile rather than the practice the previous plug tolerated. Torpedo throat castables were placed at metered water addition.

Results

Supplying the converter bottom purging assembly as a matched machined set aligned its life with the working lining, removing a forcing position that had been ending campaigns early and, in its last phase, degrading stirring quality before failure. Torpedo wear followed the zonal prediction with the throat no longer the first position to limit the car.

How the Result Was Measured

Purging assembly performance was tracked as heats per assembly, split into planned and forced changes. That split is the whole point: a plug changed on schedule at a maintenance window costs its purchase price and a crew hour, while a plug changed because it stopped blowing costs the same purchase price plus the disrupted heat and the end-point control lost while stirring was degrading. Plants that separate the two figures almost always find most of their plug cost in the forced-change column, which is where a matched assembly pays for itself. Converter lining wear was recorded by zone against the zonal prediction, and the torpedo fleet by car, so that practice variation could be separated from material variation.

What Transfers to Other Plants

When a ladle or converter bottom fails, look at the seat before the chemistry. Most bottom failures are dimensional before they are metallurgical, and the fix — a matched, verified assembly — costs far less than the campaign it protects. The second transferable point is plug selection by steel route rather than by catalogue: diffuser designs for fine clean-steel stirring with the maintenance discipline that requires, directional designs where robustness and inspection access matter more.

The purge assembly components are on the purging plug and well block pages, the transport material on the ASC brick page, and the two system views on the BOF converter and casthouse and torpedo pages.

Strict ISO 9001 Process Control Across All 6 Workshops

Every batch of raw materials is chemically assayed. Finished refractory shapes undergo density, ultrasonic non-destructive testing, and pre-assembly gap verification prior to global packaging.

  • Raw material ICP chemical assay on every incoming batch
  • Density, porosity and cold crushing (CCS) tests per ASTM / ISO
  • Ultrasonic non-destructive testing of finished shapes
  • Pre-assembly gap verification before seaworthy packaging
100,000+ Metric Tons Annual Capacity
60+ Countries Export Footprint
6 Fully-Equipped Workshops
100% ISO 9001:2015 Certified
Request Quote